+l=10//span, in m
+sigma_cbc=5//in MPa
+sigma_st=140//in MPa
+fy=250//in MPa
+m=18.66//modular ratio
+Df=100//slab thickness, in mm
+D=l*10^3/12//in mm
+D=850//approximately, in mm
+d=D-100//cover=100 mm
+bw=300//in mm
+bf=l*10^3/6+bw+6*Df//>2500 mm c/c distance of beams
+bf=2500//in mm
+W1=(bw/10^3)*(d-Df)/10^3*25//in kN/m
+W2=(Df/10^3)*(bf/10^3)*25//in kN/m
+W3=(bf/10^3)*5//imposed load, in kN/m
+W=W1+W2+W3//in kN/m
+W=24//approximately, in kN/m
+M=W*l^2/8//in kN-m
+V=W*l/2//in kN
+Ast=round(M*10^6/sigma_st/0.87/d)//in sq mm
+//provide 4-25 mm dia bars + 4-20 mm dia bars
+Ast=4*0.785*25^2+4*0.785*20^2//in sq mm
+//verification of trial section
+//assume x>Df
+x=(m*Ast*d+bf*Df^2/2)/(bf*Df+m*Ast)//in mm
+//sigma_cbc'=sigma_cbc (x-Df)/x
+a=(x-Df)/x
+z=d-(1+2*a)/(1+a)*Df/3//in mm
+sigma_st=M*10^6/Ast/z//<140 MPa, hence OK
+sigma_cbc=sigma_st/m*x/(d-x)//<5 MPa, hence OK
+Tv=V*10^3/bw/d//in MPa
+pt=Ast*100/(bw*d+(2500-300)*100)//pt=0.72, approximately
+//for M15 grade concrete and pt=0.72
+Tc=0.33//in MPa
+//as Tv>Tc, shear reinforcement required
+Vs=V-Tc*bw*d/10^3//in kN
+//provide 6 mm dia bars
+Asv=2*0.785*6^2//in sq mm
+sigma_sv=140//in MPa
+Sv=Asv*sigma_sv*d/Vs/10^3//in mm
+Sv=130//approximately, in mm
+Svmin=Asv*fy/0.4/bw//in mm
+Svmin=117//approximately, in mm
+Sv=min(Sv,Svmin)//in mm
+mprintf("T beam:bf=%d mm\nDf=%d mm\nd=%d mm\nbw=%d mm\nCover = 50 mm\nSteel= 4-25 mm dia + 4-20 mm dia bars\nStirrups = 6 mm dia @ %d mm c/c throughout",bf,Df,d,bw,Sv)