diff --git a/1943/CH1/EX1.10/Ex1_10.sce b/1943/CH1/EX1.10/Ex1_10.sce
new file mode 100755
index 000000000..f748d2aa6
--- /dev/null
+++ b/1943/CH1/EX1.10/Ex1_10.sce
@@ -0,0 +1,34 @@
+
+clf()
+clc
+clear
+//Input data
+t1x=[0,6]//Time range in hours
+t2x=[6,12]//Time range in hours
+t3=[12,14]//Time range in hours
+t4=[14,18]//Time range in hours
+t5=[18,24]//Time range in hours
+L=[30,90,60,100,50]//Load in MW
+
+//Calculations
+t1=[0,6,6,12,12,14,14,18,18,24,24]//Time in hours for Load curve
+L1=[30,30,90,90,60,60,100,100,50,50,0]//Load in MW for Load curve
+t2=[0,4,4,10,10,12,12,18,18,24,24]//Time in hours for Load duration curve
+L2=[100,100,90,90,60,60,50,50,30,30,24]//Load in MW for Load duration curve
+E=((L(1)*(t1x(2)-t1x(1)))+(L(2)*(t2x(2)-t2x(1)))+(L(3)*(t3(2)-t3(1)))+(L(4)*(t4(2)-t4(1)))+(L(5)*(t5(2)-t5(1))))//Energy generated in MWh
+AL=E/24//Average load in MW
+MD=max(L(1),L(2),L(3),L(4),L(5))//Maximum demand in MW
+LF=(AL/MD)//Load factor
+Lx=[30,10]//Loads for selecting suitable generating units in MW
+tx=[24,18,10,4]//Time for selecting suitable generating units in hrs
+PC=(Lx(1)*tx(4)+Lx(2)*1)//Plant capacity in MW
+CF=(E/(PC*24))//Capacity factor
+
+//Output
+subplot(221)
+plot(t1,L1)//Load curve taking Time in hrs on X- axis and Load in MW on Y- axis
+xtitle('Load curve','Time hrs','Load MW')
+subplot(222)
+plot(t2,L2)//Load duration curve taking Time in hrs on X- axis and Load in MW on Y- axis
+xtitle('Load duration curve','Time hrs','Load MW')
+printf('(c)Suitable generating units to supply the load are\ni)One unit of %3.0f MW will run for %3.0f hours\nii)One unit of %3.0f MW will run for %3.0f hours\niii)One unit of %3.0f MW will run for %3.0f hours\niv)One unit of %3.0f MW will run for %3.0f hours\n\n(d)Load factor is %3.2f\n\n(e)Capacity of the plant is %3.0f MW and Capacity factor is %3.3f',Lx(1),tx(1),Lx(1),tx(2),Lx(1),tx(3),Lx(2),tx(4),LF,PC,CF)